From Above: August 2019

A milestone was achieved this past month when the structural steel framing for the library and arts center reached completion.  This milestone was commemorated with a “Topping Out” event which is typically acknowledged in the construction industry when steel framing is complete and other trades can begin their work.  Metal decking has been installed on the second floor of the library and the perimeter block wall for the site is substantially complete.

From Above: March 2019



Construction continued throughout the month of March at the new Public Library and Cultural Arts Center site. Following several days of weather delays, rough grading began along with the coordination for the site utility connections on Lakeview Avenue. The piles for the North and East retaining wall shoring were installed and the Lakeview Avenue storm drain bypass is now complete.